Project Description:
PHILLIPSTON- BRIDGE BETTERMENT, P-09-005, HIGHLAND AVENUE OVER ROUTE 202/ROUTE 2
The work for the Highland Avenue Bridge shall consist of reconstructing the bridge and approach wearing surface; removing and replacing the reinforced concrete deck slab; upgrading the bridge rail; upgrading the approach guard rail; eliminating the joints over the north and south piers; checking the existing beam cover plates for fatigue and provide modifications as needed; repairing the existing substructure; and cleaning and painting the structural steel.
Location:
  • Town of Phillipston
  • Resident Engineer: William Whiteman
    Construction Contract Value: $1,563,697.00
    Construction Bid Price: $1,329,725.00
    Initial Construction Estimate: $2,373,363.00
    District: District 2

    Contracts (3) Progress
    # 36570 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 62908 -- Construction Contract
    Bridge Rehabilitation (Including Painting) (P-09-005) (Steel) - Highland Avenue over Routes 202 and 2. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/07/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/05/2007
    Project Initiation Form PIF Entered 12/13/2007
    Project Initiation Form PRC Submitted 12/13/2007
    Project Review Committee PRC Approved 03/13/2008
    Project Review Committee Letter 04/02/2008
    Project Status Advertised 12/12/2009
    Project Management
    100% Design 100% Package Received 03/09/2009
    100% Design 100% Package Comments to DE 03/11/2009
    75% Design 75% Package Received 09/26/2008
    75% Design 75% Package Comments to DE 12/11/2008
    Final Design PS&E Received 11/02/2009
    Final Design PS&E to FAPRO 11/04/2009
    Consultant Contract Process Scope to DE 06/26/2007
    Consultant Contract Process NTP Issued 06/27/2008