Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HAWLEY- BRIDGE DECK PRESERVATION, H-13-007, WEST HAWELY ROAD (ROUTE 8A) OVER CHICKLEY RIVER
The work for the West Hawley Road bridge project shall consist of removal and replacement of the reinforced concrete deck; replacement and/or repairs to stringers, end diaphragms and floor beams; upgrade capacity of controlling truss members to meet statutory loads; repair deterioration and seal cracks in the substructure; strip and paint the structural steel; provide a crash worthy rail and transition and upgrade the approach guard rail. The work shall also include milling and paving the approaches, 100’-150’.
Location:
  • Town of Hawley
  • Resident Engineer: Russell Duval
    Construction Contract Value: $2,519,682.10
    Construction Bid Price: $2,098,901.95
    Initial Construction Estimate: $3,008,384.75
    District: District 1

    Contracts (2) Progress
    # 57804 -- Construction Contract
    Bridge Rehabilitation (H-13-007) (Steel) - West Hawley Road (Route 8A) over the Chickley River. Completed
    # 77862 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/02/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/05/2007
    Project Initiation Form PIF Entered 12/05/2007
    Project Initiation Form PRC Submitted 12/05/2007
    Project Review Committee PRC Approved 03/13/2008
    Project Review Committee Letter 04/02/2008
    Project Status Advertised 11/29/2008
    Project Management
    100% Design 100% Package Received 06/06/2008
    100% Design 100% Package Comments to DE 07/30/2008
    Final Design PS&E Received 11/12/2008
    Final Design PS&E to FAPRO 11/18/2008
    Consultant Contract Process Scope to DE 10/01/2007
    Consultant Contract Process NTP Issued 11/09/2007