Project Description:
HUNTINGTON- BRIDGE BETTERMENT, H-27-006, ROUTE 112 (WORTHINGON ROAD) OVER CSX RR AND WESTFIELD RIVER
The proposed work for the bridge carrying Route 112 over the CSX RR and Westfield River consists of cleaning and painting structural steel on the main span (the thru-arch) of the Route 112 bridge over CSX RR and the Westfield River and sealing and resurfacing the existing bridge deck as identified on the plans. Additional work shall include repairing a deficient floorbeam; repairing bridge rails and other miscellaneous items required to complete the work as shown on the drawings, as listed in the proposal, as specified herein, and as directed.
Location:
  • Town of Huntington
  • Resident Engineer: Joseph Mastroianni
    Construction Contract Value: $18,608,245.24
    Construction Bid Price: $1,852,277.60
    Initial Construction Estimate: $2,469,825.00
    District: District 1

    Contracts (1) Progress
    # 56608 -- Construction Contract
    Bridge Painting and Related Work Br. No. H-27-006 Route 112 (Worthington Road) over the CSX Rail Road and the Westfield River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/01/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2007
    Project Initiation Form PIF Entered 12/19/2007
    Project Initiation Form PRC Submitted 12/24/2007
    Project Review Committee PRC Approved 03/13/2008
    Project Review Committee Letter 04/02/2008
    Project Status Advertised 07/26/2008
    Project Management
    Final Design PS&E Received 07/17/2008
    Final Design PS&E to FAPRO 07/21/2008
    Consultant Contract Process Scope to DE 05/07/2007
    Consultant Contract Process NTP Issued 06/04/2007