COLRAIN- BRIDGE PRESERVATION, C-18-005, ROUTE 112 OVER NORTH RIVER
The work for the bridge carrying Route 112 over the North River in Colrain shall consist of replacing the open steel gratings and purlins system with an 8” thick deck slab, removing deteriorated stringers, adding plates; increasing the load capacity as it is required per design for HS-20 truck loading; performing various superstructure and substructure repairs, stripping and painting the steel, and upgrading the approach guard rail.
Location:
  • Town of Colrain
  • Resident Engineer: John Bedard
    Construction Contract Value: $3,321,002.73
    Construction Bid Price: $2,485,449.50
    Initial Construction Estimate: $2,884,985.00
    District: District 1

    Contracts (2) Progress
    # 54833 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 66838 -- Construction Contract
    Bridge Reconstruction (including Painting) (C-18-005) (Steel) - Route 112 (Jacksonville Road) over the North River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/23/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2007
    Project Initiation Form PIF Entered 12/19/2007
    Project Initiation Form PRC Submitted 12/19/2007
    Project Review Committee PRC Approved 03/13/2008
    Project Review Committee Letter 04/02/2008
    Project Status Advertised 07/31/2010
    Project Management
    100% Design 100% Package Received 04/28/2009
    100% Design 100% Package Comments to DE 06/29/2009
    25% Design Design Public Hearing 07/14/2009
    Final Design PS&E Received 05/21/2010
    Final Design PS&E to FAPRO 07/01/2010
    Consultant Contract Process Scope to DE 08/06/2008
    Consultant Contract Process NTP Issued 01/23/2009
    Consultant Contract Process Workhours Approved 01/19/2009