Project Description:
BARRE- BRIDGE REPLACEMENT, B-02-005, ROUTE 122 OVER PRINCE RIVER
The work for the Route 122 Bridge over Prince River shall consist of replacing the bridge steel stringers, concrete deck, and wearing surface. The new steel stringers will be galvanized for long term protection. Upgrading the bridge rail to a crash tested steel railing system and improving the drainage along the bridge and approaches are also included in this project. Existing deteriorated steel bearings will be replaced by new neoprene type bearings. Cracks and spalled areas at the existing concrete abutments will also be repaired.
Location:
  • Town of Barre
  • Resident Engineer: Frank Penny
    Construction Contract Value: $1,798,460.00
    Construction Bid Price: $1,483,443.87
    Initial Construction Estimate: $2,034,832.00
    District: District 2

    Contracts (6) Progress
    # 41489 -- Design -- Geotechnical
    Statewide - implement geophysical methods on statewide designed and constructed bridge and highway projects. Final
    # 55039 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 64321 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69940 -- Construction Contract
    Bridge Replacement (B-02-005) (Concrete) - Route 122 (Worcester Road) over the Prince River. (ABP) Completed
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/04/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2007
    Project Initiation Form PIF Entered 12/13/2007
    Project Initiation Form PRC Submitted 12/13/2007
    Project Review Committee PRC Approved 03/13/2008
    Project Review Committee Letter 04/02/2008
    Project Status Advertised 07/16/2011
    Project Management
    100% Design 100% Package Comments to DE 05/15/2009
    25% Design 25% Package Received 01/27/2010
    25% Design 25% Package Received 06/07/2010
    25% Design 25% Package Comments to DE 03/10/2010
    25% Design 25% Package Comments to DE 03/10/2010
    25% Design 25% Package Comments to DE 06/28/2010
    25% Design Design Public Hearing 09/15/2010
    25% Design 25% Plans Complete 07/16/2010
    75% Design 75% Package Received 02/16/2011
    75% Design 75% Package Comments to DE 11/28/2008
    75% Design 75% Package Comments to DE 03/24/2011
    Final Design PS&E Received 06/24/2011
    Final Design PS&E to FAPRO 07/13/2011
    Consultant Contract Process Scope to DE 02/15/2008
    Consultant Contract Process Scope to DE 08/13/2009
    Consultant Contract Process NTP Issued 11/16/2009