Project Description:
AUBURN- BRIDGE SUPERSTRUCTURE REPLACEMENT, A-17-036 (1QN & 1QP), I-290 (EB & WB) OVER SR 12 (SOUTHBRIDGE STREET)
The work for the I-290 over Route 12 bridges shall consist of reconstructing the bridge and approach wearing surface; partially replacing the reinforced concrete deck slab; upgrading the bridge rail; upgrading the approach guard rail; eliminating the bridge joints; repairing the existing substructure; and painting the structural steel.
Location:
  • Town of Auburn
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Harry Adolphe
    Estimated Total Contract Cost: $4,469,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 59590 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2007
    Project Initiation Form PIF Entered 12/10/2007
    Project Initiation Form PRC Submitted 12/24/2007
    Project Review Committee PRC Approved 03/13/2008
    Project Review Committee Letter 04/02/2008