Project Description:
FITCHBURG- BRIDGE REPLACEMENT, F-04-003, STATE ROUTE 31 OVER PHILLIPS BROOK
The expected work for this project shall consist of, but not be limited to the following: 1. The superstructure shall be removed and replaced with precast concrete spread box beams composite with an 8" HP 4000 psi concrete deck and a 3.5" HMA wearing surface. 2. The proposed curb to curb roadway width shall be 36 feet with two 6.5 foot sidewalks 3. The minimun under clearance of the bridge cannot be reduced. 4. The existing beam seats ate to be removed and re-cast to accomodate the new superstructure using Bridge Manual details. 5. The existing bridge railing shall be removed and replaced with S3-TL4 railing 6. Major substructure cracks shall be grouted and major concrete spalls patched 7. Utility bays to accommodate all existing conduits and future utilities as required in the proposed superstructure shall be provided. 8. Abandoned steam pipeline shall be removed. 9. Existing bridge alignment shall remian unchanged.
Location:
  • City of Fitchburg
  • Construction Begins: Spring 2019
    Resident Engineer: Ryan Davison
    Construction Bid Price: $2,348,651.00
    District: District 3

    Contracts (5) Progress
    # 105916 -- Construction Contract
    Bridge Superstructure Replacement Br. No. F-04-003 (Steel) Westminster Street (Routes 2A & 31) over Phillips Brook Completed
    # 69762 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77853 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77882 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 05/02/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2007
    Project Initiation Form PIF Entered 01/02/2008
    Project Initiation Form PRC Submitted 09/28/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 09/15/2018
    Project Management
    100% Design 100% Package Received 04/23/2018
    25% Design 25% Package Received 03/06/2017
    25% Design Design Public Hearing 10/05/2017
    75% Design 75% Package Received 12/19/2017
    Final Design PS&E Received 07/02/2018
    Final Design PS&E to FAPRO 08/22/2018