Project Description:
FALL RIVER- BRIDGE BETTERMENT, F-02-045, ROUTE 24 (NB & SB) OVER BEDFORD STREET
The work for the Route 24 bridge over Bedford Street shall consist of reconstructing the bridge and approach wearing surface; replacing the reinforced concrete deck slab; extending the proposed deck at the median area for a wider bridge; replacing the reinforced concrete approach slab for a wider approach; erecting two additional beams for the widening at the median area; constructing a new reinforced concrete median; upgrading the bridge rail; upgrading the approach guard rail; replacing missing anchor bolts; and repairing the existing substructure.
Location:
  • City of Fall River
  • Resident Engineer: David Ribeiro
    Construction Contract Value: $2,775,919.00
    Construction Bid Price: $2,411,381.00
    Initial Construction Estimate: $2,972,940.00
    District: District 5

    Contracts (3) Progress
    # 37070 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/Replacement/Preservation Program. Final
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 61912 -- Construction Contract
    Bridge Replacement (F-02-045) (Steel) Route 24 NB & SB over Bedford Street. (ARRA Project) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/28/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2007
    Project Initiation Form PIF Entered 12/12/2007
    Project Initiation Form PRC Submitted 12/12/2007
    Project Review Committee PRC Approved 03/13/2008
    Project Review Committee Letter 04/02/2008
    Project Status Advertised 12/19/2009
    Project Management
    100% Design 100% Package Received 05/18/2009
    100% Design 100% Package Comments to DE 04/15/2009
    75% Design 75% Package Received 10/17/2008
    75% Design 75% Package Comments to DE 03/16/2009
    75% Design 75% Plans Complete 03/16/2009
    Final Design PS&E Received 12/04/2009
    Final Design PS&E to FAPRO 12/07/2009
    Consultant Contract Process Scope to DE 12/31/2007
    Consultant Contract Process NTP Issued 07/14/2008