FALL RIVER- SOMERSET- BRIDGE PRESERVATION, F-02-058, I-195 OVER THE COMB SR 79 & TAUNTON RIVER (BRAGA BRIDGE)
The work for the I-195 Bridge over Route 79 and the Taunton River shall consist of the repair and/or replacement of deteriorated superstructure members and connections for the floor system (no work will be performed on the truss at this time); clean (Full Removal) and paint the structural steel in the area of the repairs. Most of the members requiring repair are in the vicinity of the transverse deck joints.
Location:
  • City of Fall River
  • Town of Somerset
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $12,483,020.00
    Construction Bid Price: $10,237,896.20
    Initial Construction Estimate: $14,148,692.00
    District: District 5

    Contracts (4) Progress
    # 34493 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 5 - Contract D Final
    # 36569 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 54835 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 63039 -- Construction Contract
    Braga Bridge Superstructure Rehabilitation (F-02-058=S-16-008) - Interstate 195 over Route 79 and the Taunton River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/11/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2007
    Project Initiation Form PIF Entered 12/24/2007
    Project Initiation Form PRC Submitted 08/06/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 12/01/2008
    Project Status Advertised 02/06/2010
    Project Management
    100% Design 100% Package Received 03/06/2009
    100% Design 100% Plans Complete 08/14/2009
    Final Design PS&E Received 12/21/2009
    Final Design PS&E to FAPRO 01/25/2010
    Consultant Contract Process Scope to DE 03/01/2008
    Consultant Contract Process NTP Issued 03/27/2008