Project Description:
HANOVER- BRIDGE REPLACEMENT, H-06-011, ROUTE 53 (WASHINGTON STREET) OVER ROUTE 3 INCLUDING SIGNAL & INTERSECTION IMPROVEMENTS AT NORTHBOUND RAMPS
The work for the Route 53 over Route 3 bridge shall consist of reconstructing the bridge and approach wearing surface; replacing the superstructure and substructure; replacing the approach slab; upgrading the bridge rail; upgrading the approach guard rail; changing the structure to a two continuous span bridge by providing a new center pier and two new pier type abutments in front of the existing abutments; placing MSE walls for grade separation; and repaving the existing slope pavement. The proposed structure will measure 120’-0” long from center-to-center of bearings.
Location:
  • Town of Hanover
  • Resident Engineer: Peter Benkart
    Construction Contract Value: $8,731,961.13
    Construction Bid Price: $7,588,662.50
    Initial Construction Estimate: $9,251,196.50
    District: District 5

    Contracts (2) Progress
    # 55035 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 58512 -- Construction Contract
    Bridge Replacement (H-06-011) (Steel) - Route 53 (Washington Street) over Route 3. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/10/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2007
    Project Initiation Form PIF Entered 12/13/2007
    Project Initiation Form PRC Submitted 12/13/2007
    Project Review Committee Letter 04/03/2008
    Project Status Advertised 03/21/2009
    Project Management
    100% Design 100% Package Received 12/29/2008
    100% Design 100% Package Comments to DE 02/24/2009
    25% Design 25% Package Received 07/10/2006
    25% Design 25% Package Comments to DE 02/01/2008
    25% Design Design Public Hearing 07/15/2008
    75% Design 75% Package Received 07/08/2008
    Final Design PS&E Received 03/10/2009
    Final Design PS&E to FAPRO 03/11/2009
    Consultant Contract Process Scope to DE 08/08/2007
    Consultant Contract Process NTP Issued 02/11/2008