Project Description: |
FREETOWN- BRIDGE BETTERMENT, F-09-008, STATE ROUTE 24 OVER ASSONET RIVER
The work for the Route 24 over Assonet River bridge shall consist of replacing the entire deck, eliminate existing sidewalks, replacing existing railing and replacing existing wearing surface over a waterproofing membrane for the entire deck.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Alyson Bedard |
Estimated Total Contract Cost: | $9,086,000.00 |
Estimated Total Federal Participating Construction Cost: | $9,499,000.00 |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|