Project Description: |
FREETOWN- DECK REPLACEMENT, F-09-008, STATE ROUTE 24 OVER ASSONET RIVER
The work for the Route 24 over Assonet River bridge shall consist of replacing the entire deck, eliminate existing sidewalks, replacing existing railing and replacing existing wearing surface over a waterproofing membrane for the entire deck.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2027 |
Project Manager: | Stephen Soma |
Estimated Total Contract Cost: | $9,086,000.00 |
Estimated Total Federal Participating Construction Cost: | $9,499,000.00 |
Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization. |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|