Project Description:
LEOMINSTER- BRIDGE RECONSTRUCTION & RAMP IMPROVEMENTS, L-08-024, ROUTE 12 OVER ROUTE 2 (EB & WB)
The work for the Route 12 over Route 2 bridge shall consist of reconstructing the bridge and approach wearing surface; replacing the superstructure and bearings; replacing the approach slab; upgrading the bridge rail; upgrading the approach guard rail; modifying the center pier and the existing abutments for the new proposed superstructure and minimum clearance requirement; adjusting the roadway profile for the vertical clearance increase; modifying the existing ramps that remain and removing the existing ramps from Route 2 westbound to Route 12 and from Route 12 northbound to Route 2 eastbound; adding a modified ramp from Route 12 northbound to Route 2 Westbound; providing signals at north and south approach to the bridge.
Location:
  • City of Leominster
  • Resident Engineer: Stephen Romano
    Construction Contract Value: $8,203,110.00
    Construction Bid Price: $7,227,739.05
    Initial Construction Estimate: $8,665,495.50
    District: District 3

    Contracts (6) Progress
    # 54831 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64326 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 66702 -- Design -- Geotechnical
    Work will consist of Geotechnical design and review services for roadway and bridge projects statewide. Final
    # 75583 -- Construction Contract
    Bridge Superstructure Replacement (L-08-024) (Steel) - Route 12 (North Main Street) over the Route 2 (EB & WB) and Intersection Improvements Including Traffic Signals. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/11/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2007
    Project Initiation Form PIF Entered 12/19/2007
    Project Initiation Form PRC Submitted 12/19/2007
    Project Review Committee PRC Approved 03/13/2008
    Project Review Committee Letter 04/02/2008
    Project Status Advertised 09/15/2012
    Project Management
    25% Design 25% Package Received 12/03/2009
    25% Design 25% Package Comments to DE 03/29/2012
    25% Design Design Public Hearing 05/19/2010
    75% Design 75% Package Received 03/08/2012
    75% Design 75% Package Comments to DE 05/23/2012
    Final Design PS&E Received 08/20/2012
    Final Design PS&E to FAPRO 09/11/2012