Project Description:
BROOKLINE- INTERSECTION & SIGNAL IMPROVEMENTS @ ROUTE 9 & VILLAGE SQUARE (GATEWAY EAST)
The project is located on Route 9 in the Gateway East or Village Square area of Brookline. The project will revitalize the corridor, improve the livability for residents and businesses, improve regional connections for bicycles and pedestrians and improve the overall streetscape. The project will demolish the pedestrian bridge which is currently closed. Walnut Street will be realigned to intersection Route 9 opposite Pearl Street forming a four way intersection. The signals at Washington Street and at Brookline Avenue will be upgraded and interconnected with new signals at the Walnut/Pearl Street intersection.
Location:
  • Town of Brookline
  • Construction Begins: Spring 2019
    Resident Engineer: Pasquale Mele
    Construction Bid Price: $8,497,476.81
    District: District 6

    Contracts (1) Progress
    # 105652 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Washington (Route 9) and Walnut Streets and Adjacent Roads Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/27/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/11/2007
    Project Initiation Form PIF Entered 04/14/2010
    Project Initiation Form PRC Submitted 04/15/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Status Advertised 08/25/2018
    Project Management
    100% Design 100% Package Received 06/18/2018
    100% Design 100% Package Received 06/18/2018
    25% Design 25% Package Received 04/15/2012
    25% Design 25% Package Comments to DE 02/25/2014
    25% Design 25% Package Received - Resub 1 08/29/2016
    25% Design Design Public Hearing 04/26/2017
    75% Design 75% Package Received 12/01/2017
    75% Design 75% Package Comments to DE 01/05/2018
    Final Design PS&E Received 08/08/2018
    Final Design PS&E to FAPRO 08/09/2018