Project Description:
GROVELAND- REHABILITATION OF ROUTE 97 (SCHOOL STREET & SALEM STREET)
The project consists of the rehabilitation of Route 97 from the Georgetown line to Parker Street. Improvements include traffic safety and intersection reconfiguration at School and Salem Streets as well as bicycle and pedestrian improvements.
Location:
  • Town of Groveland
  • Construction Begins: Winter 2015/2016
    Resident Engineer: Raymond Orsini
    Construction Bid Price: $5,301,340.00
    District: District 4

    Contracts (3) Progress
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 90225 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 97 (School Street) to the Salem Street Intersection. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/21/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/18/2007
    Project Initiation Form PIF Entered 04/03/2008
    Project Initiation Form PRC Submitted 05/16/2008
    Project Review Committee PRC Approved 06/12/2008
    Project Review Committee Letter 07/11/2008
    Project Status Advertised 08/15/2015
    Project Management
    100% Design 100% Package Received 10/11/2013
    100% Design 100% Package Comments to DE 12/31/2013
    25% Design 25% Package Received 11/25/2009
    25% Design 25% Package Comments to DE 11/30/2010
    25% Design Design Public Hearing 02/16/2011
    75% Design 75% Package Received 07/22/2011
    75% Design 75% Package Comments to DE 02/06/2013
    Final Design PS&E Received 03/20/2015
    Final Design PS&E to FAPRO 08/12/2015