Project Description:
BEVERLY- SALEM- HARBORFRONT WALKWAY & CAUSEWAY PARK CONSTRUCTION
This project is for the construction of a park along the causeway of the Old Beverly-to-Salem bridge abutment in the City of Salem. Work includes the construction of a pedestrian fishing area, walkway, benches, trash receptacles and lighting as necessary.
Location:
  • City of Salem
  • Resident Engineer: Susan Cranney
    Construction Contract Value: $1,831,399.00
    Construction Bid Price: $1,658,295.00
    Initial Construction Estimate: $1,965,575.00
    District: District 4

    Contracts (5) Progress
    # 45688 -- Design -- Hwy Eng Open End
    Work will generally consist of providing engineering design and review services to the Projects Division on an open end basis for various statewide highway and bridge projects Final
    # 51301 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 79143 -- Construction Contract
    Construction of Harbor Front Walkway and Causeway Park along the Danvers River. Terminated

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/16/2008
    Project Initiation Form PIF Entered 01/17/2008
    Project Initiation Form PRC Submitted 01/23/2008
    Project Review Committee PRC Approved 04/14/1998
    Project Status Advertised 08/10/2013
    Project Management
    100% Design 100% Package Received 01/08/2013
    100% Design 100% Package Comments to DE 03/07/2013
    25% Design 25% Package Received 10/03/2008
    25% Design 25% Package Comments to DE 05/01/2009
    25% Design Design Public Hearing 06/02/2009
    75% Design 75% Package Received 06/06/2011
    75% Design 75% Package Received 03/26/2012
    75% Design 75% Package Received 03/27/2012
    75% Design 75% Package Comments to DE 10/31/2012
    Final Design PS&E Received 07/02/2013
    Final Design PS&E to FAPRO 07/17/2013
    Consultant Contract Process NTP Issued 11/16/2009