Project Description:
MEDFORD- IMPROVEMENTS & REALIGNMENT ON CLIPPERSHIP DRIVE
Clippership Drive is currently two lanes with a sweeping alignment that encourages excessive speeds near an elderly housing complex. The master plan for Medford Square proposes to reduce the roadway width on Clippership Drive by eliminating one lane and providing a parking lane. Sidewalks will be provided on both sides of Clippership Drive with granite curbing. The current project would also realign Clippership Drive away from the Mystic River to create more park space, while providing traffic calming near the elderly housing complex by removing the sweeping curve and introducing a stop condition on Clippership Drive. This alignment would also define development parcels along Clippership Drive.
Location:
  • City of Medford
  • Resident Engineer: John McGillicuddy
    Construction Contract Value: $1,595,144.00
    Construction Bid Price: $1,545,286.15
    Initial Construction Estimate: $1,779,680.00
    District: District 4

    Contracts (1) Progress
    # 62562 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Clippership Drive (ARRA) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/11/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/17/2008
    Project Initiation Form PIF Entered 02/14/2008
    Project Initiation Form PRC Submitted 02/26/2008
    Project Review Committee PRC Approved 03/13/2008
    Project Review Committee Letter 04/03/2008
    Project Status Advertised 01/23/2010
    Project Management
    100% Design 100% Package Received 09/14/2009
    100% Design 100% Package Comments to DE 11/04/2009
    25% Design 25% Package Received 04/24/2008
    25% Design Design Public Hearing 11/05/2008
    75% Design 75% Package Received 12/30/2008
    75% Design 75% Package Comments to DE 03/12/2009
    Final Design PS&E Received 12/11/2009
    Final Design PS&E to FAPRO 01/20/2010