Project Description:
WARE- BRIDGE REPLACEMENT, W-05-015, ROUTE 32 (PALMER ROAD) OVER THE WARE RIVER
Work under this Contract consists of replacing the existing State Route 32 (Palmer Road) bridge in the Town of Ware. The work includes complete replacement of the existing bridge, as well as reconstruction and realignment of Palmer Road with modifications of the roadway profile and right of way. The project includes, but is not limited to, pedestrian facilities, ADA ramps, and new striping in accordance with the Contract plans and documents. Existing utility poles carrying overhead telephone, electric, and cable lines along Route 32 (Palmer Road) are to be relocated, and the existing 12-inch diameter water main on the bridge will be replaced with a new 12-inch water main. Temporary use of the existing 6-inch diameter water main will provide service during staged construction. The existing 3-span bridge will be completely demolished and replaced with a two-span continuous steel girder bridge supported on integral abutments and a center pier, all on steel piles.
Location:
  • Town of Ware
  • Construction Begins: Winter 2022/2023
    Resident Engineer: Jason Shunaman
    Construction Bid Price: $11,186,879.00
    District: District 2

    Contracts (2) Progress
    # 120185 -- Construction Contract
    Bridge Replacement Br. No. W-05-015 (Steel) Route 32 (Palmer Road) over the Ware River
    # 77871 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/28/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/28/2008
    Project Initiation Form PIF Entered 02/01/2008
    Project Initiation Form PRC Submitted 04/02/2008
    Project Review Committee PRC Approved 06/12/2008
    Project Review Committee Letter 07/11/2008
    Project Status Advertised 09/10/2022
    Project Management
    100% Design 100% Package Received 08/10/2021
    100% Design 100% Package Comments to DE 09/13/2021
    25% Design 25% Package Received 06/29/2020
    25% Design 25% Package Comments to DE 07/27/2020
    25% Design Design Public Hearing 02/10/2021
    75% Design 75% Package Received 01/19/2021
    75% Design 75% Package Comments to DE 02/19/2021
    Final Design PS&E Received 08/19/2022
    Final Design PS&E to FAPRO 08/30/2022
    Consultant Contract Process Scope to DE 04/01/2008