Project Description:
WESTFIELD- RESURFACING & RELATED WORK ON ROUTE 10/202
The project consists of cold planing and resurfacing two sections of Route 202 in Westfield. Section 1 is a state-owned route, it begins at the Dion Way intersection, a distance of 200 feet north of mile marker 11.7 and proceeds northerly to the North Road intersection, 260 feet north of mile marker 14.4; the length of this section is 14,300 feet (2.71 miles). Section 2 of Route 202 is a municipally-owned route; it begins at this intersection and continues to mile marker 15.9 for a distance of 7,660 feet (1.45 miles). The project also consists of milling 2" from the existing roadway surface, applying tack coat and resurfacing with 2" of HMA Modified Top Course. New pavement markings and temporary traffic controls for construction operations will be included.
Location:
  • City of Westfield
  • Resident Engineer: Daniel Boucher
    Construction Contract Value: $1,625,880.00
    Construction Bid Price: $1,353,082.00
    Initial Construction Estimate: $1,583,000.00
    District: District 2

    Contracts (1) Progress
    # 56323 -- Construction Contract
    The project consists of cold planing and resurfacing two sections of Route 202 in Westfield. Section 1 on Southampton Road and Section 2 on North Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/08/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/30/2008
    Project Initiation Form PIF Entered 01/31/2008
    Project Initiation Form PRC Submitted 02/25/2008
    Project Review Committee PRC Approved 03/13/2008
    Project Status Advertised 06/28/2008
    Project Management
    Final Design PS&E Received 05/28/2008
    Final Design PS&E to FAPRO 06/10/2008