| Project Description: |
ATTLEBORO- RECONSTRUCTION & GEOMETRIC IMPROVEMENTS ON TIFFANY STREET, FROM ROUTE 123 TO NEW ROAD (PHASE II), INCLUDES CULVERT RECONSTRUCTION OF A-16-077
Work on this project consists of box cut widening, milling and overlay of Tiffany Street. Traffic signals upgrading is also proposed at the Route 123 (South Street)/Tiffany Street intersection. Other related work includes culvert reconstruction and replacement, drainage upgrades, sidewalk installation, and pavement markings.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Municipality |
| Project Manager: | Michael-kosmas Bloukos![]() |
| Estimated Total Contract Cost: | $3,293,667.45 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 5 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||