Project Description:
METHUEN- GUARDRAIL, SIGN & PAVEMENT MARKING IMPROVEMENTS ON ROUTE 213
Safety improvement project along Route 213 in Methuen. The median will be regraded and high tension cable guardrail will be installed. Signing and pavement marking improvements will also be included.
Location:
  • Town of Methuen
  • Resident Engineer: Peter Gfatter
    Construction Contract Value: $827,244.00
    Construction Bid Price: $714,767.93
    Initial Construction Estimate: $759,449.55
    District: District 4

    Contracts (1) Progress
    # 60372 -- Construction Contract
    Cable Barrier Installation Along a Section of Route 213. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/30/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2008
    Project Initiation Form PIF Entered 03/25/2008
    Project Initiation Form PRC Submitted 06/25/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 11/18/2008
    Project Status Advertised 09/12/2009
    Project Management
    100% Design 100% Package Received 08/21/2009
    100% Design 100% Package Comments to DE 09/01/2009
    75% Design 75% Package Received 07/25/2009
    75% Design 75% Package Comments to DE 08/18/2009
    Final Design PS&E Received 09/04/2009
    Final Design PS&E to FAPRO 09/04/2009