Project Description:
AMHERST- NORTHAMPTON- SOUTHAMPTON- SIDEWALK & WHEELCHAIR RAMP CONSTRUCTION ON ROUTES 5, 9, & 10
The work for this project will consist of constructing new sidewalks and wheelchair ramps in the following 4 locations: on the south side of Route 9 in Amherst from the Hadley Town Line to Snell Street and on the north side of Route 9 from the Hadley Town Line to University Drive, on the west side of Route 5/10 in Northampton from Bridge Road to Pine Brook Street and on the west side of Route 10 in Southampton from the Southampton fire station to the gas station just south of Clark Street. Other proposed work will include improvements to pedestrian accommodations, driveway reconstruction, pavement markings and crosswalks, and new signage.
Location:
  • Town of Amherst
  • City of Northampton
  • Town of Southampton
  • Resident Engineer: Mark Joy
    Construction Contract Value: $678,788.12
    Construction Bid Price: $600,877.75
    Initial Construction Estimate: $531,000.00
    District: District 2

    Contracts (3) Progress
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 84997 -- Construction Contract
    Construction of Sidewalk and Wheel Chair Ramps along Sections of Routes 5, 9 and 10 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/11/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/13/2008
    Project Initiation Form PIF Entered 02/19/2008
    Project Initiation Form PRC Submitted 03/10/2008
    Project Review Committee PRC Approved 03/13/2008
    Project Review Committee Letter 04/02/2008
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 02/27/2014
    100% Design 100% Package Comments to DE 03/12/2014
    25% Design 25% Package Received 05/03/2013
    25% Design 25% Package Comments to DE 06/05/2013
    25% Design Design Public Hearing 10/17/2013
    75% Design 75% Package Received 12/11/2013
    75% Design 75% Package Comments to DE 01/22/2014
    Final Design PS&E Received 07/01/2014
    Final Design PS&E Received 08/19/2014
    Final Design PS&E to FAPRO 09/15/2014
    Consultant Contract Process NTP Issued 08/17/2012