Project Description:
HINGHAM- IMPROVEMENTS ON ROUTE 3A, FROM OTIS STREET/COLE ROAD INCLUDING SUMMER STREET AND ROTARY, ROCKLAND STREET TO GEORGE WASHINGTON BOULEVARD
Work on this project includes a potential road diet along the corridor to reduce the 4-lane cross section to 2-lanes for the purpose of providing bike accommodation. The project will also provide improved pedestrian accommodation in the form of ADA compliant walkways both sides of the roadway (and possible expansion of an existing sidewalk into a shared use path along the water front) where feasible. Traffic signal improvements are proposed at 4 locations: 3A/North St.; Summer St./Martins Lane; Rockland Street/George Washington Blvd.; and, the existing ground mounted traffic signals on 3A at the North entrance/exit to the Public Beach parking area. In addition, the Route 3A (Summer Street) rotary is proposed for improvements, the preferred alternative being a modern roundabout over signalization. The project may also introduce a planted/landscaped median island along a section of the corridor (Summer Street portion). Finally, storm water management improvements, new signage and pavement markings are also proposed.
Location:
  • Town of Hingham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: Janhavi Limaye
    Estimated Total Contract Cost: $27,188,542.83
    Estimated Total Federal Participating Construction Cost: $31,949,530.68
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 5
    Current Status: 75% Package Comments to DE (as of 04/29/2024 )

    Contracts (1) Progress
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: HINGHAM
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $28,738,432(STBG, TAP,NHPP)
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $9,390,745.60
    State Cost: $2,347,686.40
    Total Cost: $11,738,432.00

    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: HINGHAM
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $28,738,432(STBG, TAP,NHPP)
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,600,000.00
    State Cost: $400,000.00
    Total Cost: $2,000,000.00

    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: HINGHAM
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $28,738,432(STBG, TAP,NHPP)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $12,000,000.00
    State Cost: $3,000,000.00
    Total Cost: $15,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/18/2008
    Project Initiation Form PIF Entered 07/17/2009
    Project Initiation Form PRC Submitted 07/27/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/10/2009
    Project Management
    25% Design 25% Package Received 03/29/2019
    25% Design 25% Package Comments to DE 11/30/2021
    25% Design Design Public Hearing 01/11/2022
    75% Design 75% Package Received 02/13/2024
    75% Design 75% Package Comments to DE 04/29/2024