Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
FREETOWN- LAKEVILLE- TAUNTON- RESURFACING & RELATED WORK ON ROUTE 140
The purpose of this project is to mill nad resurface various sections of Route 140 in Freetown, Lakeville and Taunton.
Location:
  • Town of Freetown
  • Town of Lakeville
  • City of Taunton
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Albert Li
    Estimated Total Contract Cost: $12,697,908.98
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • F09019 
    • F09022 
    • L01009 
    • L01013 
    See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project