Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BILLERICA- REHABILITATION ON BOSTON ROAD (ROUTE 3A) FROM BILLERICA TOWN CENTER TO FLOYD STREET
The proposed improvements will provide a consistent cross section of four lanes with shoulders and sidewalks between the Town center and Floyd Street. New traffic signals will be installed. Improved access will be implemented. Drainage will be upgraded. The Town Center will be reconfigured and signals upgraded to improve traffic operations.
Location:
  • Town of Billerica
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2022
    Project Manager: Gregory Mischel
    Estimated Total Contract Cost: $10,858,650.00
    Estimated Total Federal Participating Construction Cost: $11,981,872.50
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization.
    District: District 4
    Current Status: 100% Package Received (as of 08/03/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: BILLERICA
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $1,142,568.00
    State Cost: $285,642.00
    Total Cost: $1,428,210.00

    Planned Federal FY: 2023
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: BILLERICA
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $225,527.20
    State Cost: $56,381.80
    Total Cost: $281,909.00

    Planned Federal FY: 2023
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: BILLERICA
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $2,044,240.00
    State Cost: $511,060.00
    Total Cost: $2,555,300.00

    Planned Federal FY: 2023
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: BILLERICA
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $5,665,471.20
    State Cost: $1,416,367.80
    Total Cost: $7,081,839.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/05/2008
    Project Initiation Form PIF Entered 06/01/2009
    Project Initiation Form PRC Submitted 06/30/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Management
    100% Design 100% Package Received 08/03/2021
    25% Design 25% Package Received 10/09/2018
    25% Design 25% Package Comments to DE 06/28/2019
    25% Design 25% Package Received - Resub 1 11/14/2019
    25% Design Design Public Hearing 09/30/2020
    75% Design 75% Package Received 02/22/2021
    75% Design 75% Package Comments to DE 03/31/2021