Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BILLERICA- REHABILITATION ON BOSTON ROAD (ROUTE 3A) FROM BILLERICA TOWN CENTER TO FLOYD STREET
The proposed improvements will provide a consistent cross section of four lanes with shoulders and sidewalks between the Town center and Floyd Street. New traffic signals will be installed. Improved access will be implemented. Drainage will be upgraded. The Town Center will be reconfigured and signals upgraded to improve traffic operations.
Location:
  • Town of Billerica
  • Construction Begins: Spring 2022
    Resident Engineer: Dylan Giles
    Construction Bid Price: $11,334,198.79
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization.
    District: District 4
    Current Status: J. Tropeano Inc. will continue drainage structure installation along the east side of Boston Road working towards town center. Dagle Electric will begin mast arm foundation installation. Asplundh Construction will be complete with all utility relocations. New England Utility Constructors (NEUCO) will continue gas main relocation on Boston Road, Good Street and Farmers Lane. (as of 05/15/2023)

    Contracts (1) Progress
    # 117600 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on a Section of Boston Road (Route 3A)

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/02/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    Planned Federal FY: 2023
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: BILLERICA
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Total Cost: $13,269,348; AC Year 2 of 2. Advertised on 3/19/22. TEC: 8.60 out of 16.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,726,494.40
    State Cost: $1,181,623.60
    Total Cost: $5,908,118.00

    Planned Federal FY: 2023
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: BILLERICA
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Total Cost: $13,269,348; AC Year 2 of 2. Advertised on 3/19/22. TEC: 8.60 out of 16.
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $1,244,240.00
    State Cost: $311,060.00
    Total Cost: $1,555,300.00

    Planned Federal FY: 2023
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: BILLERICA
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Total Cost: $13,269,348; AC Year 2 of 2. Advertised on 3/19/22. TEC: 8.60 out of 16.
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $225,527.20
    State Cost: $56,381.80
    Total Cost: $281,909.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/05/2008
    Project Initiation Form PIF Entered 06/01/2009
    Project Initiation Form PRC Submitted 06/30/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Status Advertised 03/19/2022
    Project Management
    100% Design 100% Package Received 08/03/2021
    100% Design 100% Package Comments to DE 09/13/2021
    25% Design 25% Package Received 10/09/2018
    25% Design 25% Package Comments to DE 06/28/2019
    25% Design 25% Package Received - Resub 1 11/14/2019
    25% Design Design Public Hearing 09/30/2020
    75% Design 75% Package Received 02/22/2021
    75% Design 75% Package Comments to DE 03/31/2021
    Final Design PS&E Received 12/13/2021
    Final Design PS&E Received - Resub 1 02/10/2022
    Final Design PS&E Received - Resub 2 02/25/2022