METHUEN- SIGNAL IMPROVEMENTS ON ROUTE 110 @ RIVERSIDE DRIVE & BOLDUC STREET (SHORT TERM IMPROVEMENTS TO METHUEN ROTARY)
The project will address a critical shortcoming in an area identified by the Methuen Rotary Study. The project consists of constructing a traffic signal at the intersection of Route 110 with Riverside Drive.
Location:
  • Town of Methuen
  • Resident Engineer: Kenneth Wong
    Construction Contract Value: $820,200.11
    Construction Bid Price: $234,380.00
    Initial Construction Estimate: $261,187.75
    District: District 4

    Contracts (2) Progress
    # 54826 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 69630 -- Construction Contract
    METHUEN - Traffic Signal Improvements and Related Work Route 110 (Lowell Street) at Intersection with Riverside Drive and Bolduc Street (Methuen Rotary) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/19/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2008
    Project Initiation Form PIF Entered 05/07/2008
    Project Initiation Form PRC Submitted 05/19/2008
    Project Review Committee PRC Approved 06/12/2008
    Project Review Committee Letter 07/11/2008
    Project Status Advertised 04/03/2010
    Project Status Advertised 07/02/2011
    Project Management
    100% Design 100% Package Received 10/15/2009
    100% Design 100% Package Comments to DE 02/03/2010
    25% Design 25% Package Received 01/23/2009
    25% Design 25% Package Comments to DE 06/08/2009
    25% Design Design Public Hearing 06/23/2009
    Final Design PS&E Received 03/01/2010
    Final Design PS&E to FAPRO 03/31/2010
    Consultant Contract Process NTP Issued 06/09/2008
    Consultant Contract Process Workhours Approved 06/09/2008