ANDOVER- CONSTRUCTION OF MAINTENANCE FACILITY AT INTERCHANGE OF I-93 AND RIVER ROAD
Work will consist of relocating the maintenance facility from interchange of I-93 / I-495 to I-93 / River Road in Andover for salt contamination mitigation.
Location:
  • Town of Andover
  • Resident Engineer: Robert Blackmar
    Construction Contract Value: $5,178,100.00
    Construction Bid Price: $4,691,000.00
    Initial Construction Estimate: $4,591,500.00
    District: District 4

    Contracts (2) Progress
    # 61532 -- Design -- Services
    Work will consist of repairs and renovations to existing buildings. Final
    # 75769 -- Construction Contract
    Construction of a MassDOT Maintenance Facility at Interstate 93 and River Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/04/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/08/2008
    Project Initiation Form PIF Received 05/12/2011
    Project Initiation Form PIF Entered 10/31/2011
    Project Initiation Form PRC Submitted 10/31/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 09/29/2012
    Project Management
    100% Design 100% Package Comments to DE 08/22/2012
    Final Design PS&E Received 08/23/2012
    Final Design PS&E to FAPRO 09/11/2012