Project Description:
WALPOLE- SIDEWALK RECONSTRUCTION & RELATED WORK ON WASHINGTON STREET
Work on this project includes new construction and reconstruction of sidewalks on Washington Street between School Meadow Brook and Water Street. The project also includes reconstruction of a culvert and drainage improvements.
Location:
  • Town of Walpole
  • Resident Engineer: Brian Lewis
    Construction Contract Value: $1,242,788.79
    Construction Bid Price: $995,623.86
    Initial Construction Estimate: $1,273,969.39
    District: District 5

    Contracts (2) Progress
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70093 -- Construction Contract
    Roadway Reconstruction (Including Sidewalks) on a Section of Washington Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/09/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2008
    Project Initiation Form PIF Entered 05/16/2008
    Project Initiation Form PRC Submitted 05/27/2008
    Project Review Committee PRC Approved 06/12/2008
    Project Review Committee Letter 07/11/2008
    Project Status Advertised 07/23/2011
    Project Management
    100% Design 100% Package Received 03/28/2011
    100% Design 100% Package Comments to DE 06/03/2011
    25% Design 25% Package Received 11/30/2009
    25% Design 25% Package Comments to DE 02/02/2010
    25% Design Design Public Hearing 05/27/2010
    75% Design 75% Package Received 09/30/2010
    75% Design 75% Package Comments to DE 12/28/2010
    Final Design PS&E Received 06/24/2011
    Final Design PS&E to FAPRO 07/19/2011