Project Description:
DISTRICT 5- UPGRADES AND REPAIRS TO TRAFFIC SIGNAL SYSTEMS
Work on this project consists of traffic signal upgrades and repairs at various locations on state highway.
Location:
Resident Engineer: Patrick McKenna
Construction Contract Value: $641,693.85
Construction Bid Price: $449,299.00
Initial Construction Estimate: $535,342.50
District: District 5

Contracts (1) Progress
# 61176 -- Construction Contract
Traffic Signal Improvement at Various Locations. (RE-ADVERTISED) 100% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/16/2010
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/19/2008
    Project Initiation Form PIF Entered 10/03/2008
    Project Initiation Form PRC Submitted 10/03/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 12/03/2008
    Project Status Advertised 03/14/2009
    Project Status Advertised 09/12/2009
    Project Management
    Final Design PS&E Received 01/06/2009
    Final Design PS&E Received 09/02/2009
    Final Design PS&E to FAPRO 03/05/2009
    Final Design PS&E to FAPRO 09/02/2009