Project Description:
MILTON- BRIDGE BETTERMENT, M-25-028, PONKAPOAG TRAIL OVER I-93/US-1
The work for the Ponkapoag Trail Bridge over I-93/US-1 shall consist of reconstructing the bridge and approach wearing surface; replacing the reinforced concrete deck slab and shear connectors; upgrading the bridge rail and protective screen; upgrading the approach guard rail; providing a new strip seal joint at abutments; providing a new approach slab; modifying the top of backwall for new joint; repairing the minor deteriorations at the abutments; and stripping and painting the structural steel.
Location:
  • Town of Milton
  • Resident Engineer: Anthony Neve
    Construction Contract Value: $3,784,028.20
    Construction Bid Price: $3,152,524.00
    Initial Construction Estimate: $3,529,880.80
    District: District 4

    Contracts (3) Progress
    # 37070 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/Replacement/Preservation Program. Final
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57758 -- Construction Contract
    Bridge Reconstruction (M-25-028) (Steel) - Ponkapoag Trail over I-93 and Route 1. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/06/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/21/2008
    Project Initiation Form PIF Entered 05/21/2008
    Project Initiation Form PRC Submitted 05/21/2008
    Project Status Advertised 10/18/2008
    Project Management
    100% Design 100% Package Received 06/18/2008
    100% Design 100% Package Comments to DE 07/11/2008
    Final Design PS&E Received 09/29/2008
    Final Design PS&E to FAPRO 10/07/2008
    Consultant Contract Process Scope to DE 02/17/2006
    Consultant Contract Process NTP Issued 03/27/2006