Project Description:
SOMERVILLE- STREETSCAPE IMPROVEMENTS ON BROADWAY
The project will reconstruct Broadway from Garfield Avenue to the Boston City Line. The roadway will be narrowed from four lanes to two lanes with marked bike lanes. The work includes wider sidewalks, pedestrian scale lighting, improved crosswalks with bump outs, bus stops and roadway realignment to create pedestrian activity nodes. Other amenities include bike racks, benches and landscaping.
Location:
  • City of Somerville
  • Resident Engineer: George Kavalaris
    Construction Contract Value: $4,141,035.61
    Construction Bid Price: $7,917,175.70
    Initial Construction Estimate: $6,921,906.00
    District: District 4

    Contracts (2) Progress
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 71102 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Streetscape Enhancements) on a Section of Broadway. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/29/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/04/2008
    Project Initiation Form PIF Entered 09/16/2008
    Project Initiation Form PRC Submitted 09/30/2008
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/08/2009
    Project Status Advertised 09/17/2011
    Project Management
    100% Design 100% Package Received 07/05/2011
    100% Design 100% Package Comments to DE 08/26/2011
    25% Design 25% Package Received 05/06/2010
    25% Design 25% Package Comments to DE 11/08/2010
    25% Design Design Public Hearing 03/03/2011
    75% Design 75% Package Received 05/06/2010
    75% Design 75% Package Comments to DE 11/08/2010
    Final Design PS&E Received 09/09/2011
    Final Design PS&E to FAPRO 09/14/2011