FALL RIVER- INTERCHANGE IMPROVEMENTS AT ROUTE I-195/ROUTE 79/ROUTE 138 INCLUDING BRAGA BRIDGE PHASE 2 CLEANING/PAINTING AND STRUCTURAL REPAIRS
Work on this project consists of reconfiguration of the Route I-195/Route 79/Route 138 interchange including all ramps and associated bridges. A primary objective of this project is to provide safety improvements and eliminate structurally deficient bridges. The existing bridge structures will be removed and replaced with new bridges and at-grade roadways. The project includes safety improvements by eliminating substandard weaving areas and providing positive control at intersections. Regional connectivity will be maintained while improving local access. Bicycle and pedestrian access will also be improved. In addition the Design-Build project will include the addition of Braga Bridge Phase 2 Cleaning/Painting and Structural Repairs
Location:
  • City of Fall River
  • Construction Begins: Summer 2013
    Resident Engineer: Emanuel Aguiar
    Construction Contract Value: $227,987,382.33
    Construction Bid Price: $197,349,100.00
    Initial Construction Estimate: $230,000,000.00
    District: District 5

    Contracts (18) Progress
    # 49402 -- Design -- Hwy Eng Open End
    Work will generally consist of providing design and engineering services to the Projects Division on an open end basis for various statewide Value Engineering Studies. Final
    # 51301 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 55034 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57730 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 57731 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 62936 -- Non-system contract type
    Statewide-Owner's Representative-Will perform peer reviews and manage cost recovery and value engineering on various projects.
    # 64313 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64317 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 65757 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 73768 -- Construction Contract
    Route 79 / Interstate 195 Interchange Reconstruction (Including Bridges F-02-013, 014, 016, 059, 093) Over Route 138 (Davol Street) and Structural Repairs and Painting of Brag Completed
    # 76262 -- Non-system contract type
    Perform various assignments as the Owner's Representative for the peer review of engineering elements associated with satewide construction projects.
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80655 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

    Contract Dates
    Notice to Proceed: 08/26/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/09/2008
    Project Initiation Form PIF Entered 06/09/2008
    Project Initiation Form PRC Submitted 06/09/2008
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 11/25/2008
    Project Review Committee Resubmitted 05/19/2011
    Project Status Advertised 12/28/2012
    Project Management
    25% Design 25% Package Received 03/02/2012
    25% Design Design Public Hearing 01/09/2013
    Final Design PS&E Received 12/28/2012
    Consultant Contract Process Scope to DE 08/08/2008