Project Description:
DISTRICT 4- SCHEDULED & EMERGENCY STRUCTURAL REPAIRS (NORFOLK & SUFFOLK COUNTIES - CONTRACT #3)
These projects are continuously required for the maintenance and repairs to various bridges in District Four and to respond to emergencies and chipping of loose concrete after the freeze/thaw cycles.
Location:
Resident Engineer: Patrick Mannion
Construction Contract Value: $8,033,020.00
Construction Bid Price: $3,203,020.00
Initial Construction Estimate: $3,398,000.00
District: District 4

Contracts (1) Progress
# 56589 -- Construction Contract
District 4 - Scheduled and Emergency Bridge Structural Repairs at Various Locations (Norfolk & Suffolk Counties) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/01/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/10/2008
    Project Initiation Form PIF Entered 06/10/2008
    Project Initiation Form PRC Submitted 06/10/2008
    Project Review Committee PRC Approved 06/12/2008
    Project Review Committee Letter 06/12/2008
    Project Status Advertised 08/02/2008
    Project Management
    Final Design PS&E Received 07/07/2008
    Final Design PS&E to FAPRO 07/22/2008
    Consultant Contract Process Scope to DE 01/07/2008
    Consultant Contract Process NTP Issued 01/21/2008