Project Description:
FRAMINGHAM- BRIDGE REPLACEMENT, F-07-001, ROUTE 9 (WORCESTER ROAD) OVER RESERVOIR OUTLET
The purpose of this project is to replace the superstructure of the Route 9 bridge over the Reservoir Outlet connecting the Foss Reservoir No. 3 to the Stearnes Reservoir No. 1.
Location:
  • Town of Framingham
  • Resident Engineer: Neil Ahearn
    Construction Contract Value: $10,388,249.04
    Construction Bid Price: $7,563,773.50
    Initial Construction Estimate: $8,205,355.35
    District: District 3

    Contracts (5) Progress
    # 59591 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 64314 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 66702 -- Design -- Geotechnical
    Work will consist of Geotechnical design and review services for roadway and bridge projects statewide. Final
    # 69759 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 80985 -- Construction Contract
    Bridge Replacement (F-07-001) (Steel) - Route 9 (Worcester Road) over Reservoir Outlet (using Accelerated Bridge Construction Techniques). (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/18/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/01/2008
    Project Initiation Form PIF Entered 07/01/2008
    Project Initiation Form PRC Submitted 07/01/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 12/01/2008
    Project Status Advertised 01/18/2014
    Project Management
    25% Design 25% Package Received 03/06/2013
    25% Design 25% Package Comments to DE 01/30/2012
    25% Design Design Public Hearing 07/25/2013
    75% Design 75% Package Received 08/20/2013
    75% Design 75% Package Comments to DE 10/16/2014
    Final Design PS&E Received 11/29/2013
    Final Design PS&E to FAPRO 01/15/2014
    Consultant Contract Process Scope to DE 01/28/2010
    Consultant Contract Process NTP Issued 06/03/2011