Project Description:
FLORIDA- SAVOY- BRIDGE PRESERVATION, F-05-005=S-06-010, ROUTE 2 OVER THE COLD RIVER
The work for the Route 2 Bridge over the Cold River shall consist of reconstructing the approach wearing surface; removal and replacement of the reinforced concrete deck slab; removal and replacement of the existing spirals; upgrading the bridge rail; upgrading the approach guard rail; provide Strip seal joint over westerly abutment and saw cut at the easterly abutment; removal and replacement of the broken connection angles and diaphragms; removal and replacement of the rocker bearings with new reinforced elastomeric bearing pads; Repair the beam ends, add plates as required; repair the existing substructure ; clean (overcoat) and paint the structural steel bottom flange as well as the ends for 10’-0”.
Location:
  • Town of Florida
  • Town of Savoy
  • Resident Engineer: Michael Wall
    Construction Contract Value: $2,593,765.00
    Construction Bid Price: $2,190,078.00
    Initial Construction Estimate: $3,641,819.00
    District: District 1

    Contracts (2) Progress
    # 54832 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 68155 -- Construction Contract
    Bridge Rehabilitation (Including Painting) (F-05-005=S-06-010) (Steel) - Route 2 (Mohawk Trail) over the Cold River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/27/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/18/2008
    Project Initiation Form PIF Entered 07/18/2008
    Project Initiation Form PRC Submitted 09/25/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 12/01/2008
    Project Status Advertised 01/08/2011
    Project Management
    100% Design 100% Package Received 05/12/2009
    Final Design PS&E Received 11/19/2009
    Final Design PS&E to FAPRO 12/10/2010