Project Description:
YARMOUTH- INTERSECTION IMPROVEMENTS AT OLD TOWN HOUSE ROAD AND FOREST ROAD
The proposed project consists of traffic signal installation and associated geometric improvements to address traffic safety issues at the intersection of Old Town House Road and Forest Road.
Location:
  • Town of Yarmouth
  • Resident Engineer: Michael King
    Construction Contract Value: $1,106,689.00
    Construction Bid Price: $946,440.51
    Initial Construction Estimate: $1,060,940.50
    District: District 5

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 72754 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) at Old Town House Road and Forest Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/17/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/30/2008
    Project Initiation Form PIF Entered 07/31/2008
    Project Initiation Form PRC Submitted 09/30/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 11/18/2008
    Project Status Advertised 02/18/2012
    Project Management
    100% Design 100% Package Received 03/07/2011
    100% Design 100% Package Received 12/16/2011
    100% Design 100% Package Comments to DE 07/19/2011
    100% Design 100% Package Comments to DE 01/06/2012
    100% Design 100% Package Rejected 07/19/2011
    25% Design 25% Package Received 12/18/2008
    25% Design 25% Package Received 08/29/2009
    25% Design 25% Package Comments to DE 03/05/2010
    25% Design 25% Package Rejected 02/06/2009
    25% Design Design Public Hearing 04/29/2010
    75% Design 75% Package Received 07/14/2010
    75% Design 75% Package Comments to DE 09/08/2010
    Final Design PS&E Received 02/13/2012
    Final Design PS&E to FAPRO 02/15/2012