Project Description:
MILTON- CAMERA & RTMS DETECTOR ON I-93 AT EAST MILTON SQUARE
This project involves installing two 40 foot tall Steel Poles, each with pan-tilt-zoom CCTV cameras, at the northern and southern sections of I-93 adjacent to the East Milton Square covered section of I-93. The purpose of these CCTV cameras is to view the roadway area beneath the East Milton Square overpass and the adjacent areas and report to the MassDOT Traffic Operations Center. There shall also be one (1) radar based traffic sensor installed on the southern ITS Pole, and two (2) radar based traffic sensors installed on the northern ITS Pole for traffic measurements across all lanes of I-93 traffic both northbound and southbound including the HOV lanes. Traffic measurements shall include: volume, speed, headway, gap, occupancy, vehicle classification and presence and reported to the MassDOT Traffic Operation Center.
Location:
  • Town of Milton
  • Resident Engineer: Robert Ballasty
    Construction Contract Value: $303,338.00
    Construction Bid Price: $248,825.00
    Initial Construction Estimate: $225,845.00
    District: District 4

    Contracts (2) Progress
    # 57731 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 59864 -- Construction Contract
    Intelligent Transportation Systems Installation on Interstate 93 at East Milton Square Terminated

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/30/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/30/2008
    Project Initiation Form PIF Entered 07/30/2008
    Project Initiation Form PRC Submitted 07/30/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 11/18/2008
    Project Status Advertised 07/25/2009
    Project Management
    100% Design 100% Package Received 04/08/2009
    75% Design 75% Package Received 10/15/2008
    Final Design PS&E Received 06/04/2009
    Final Design PS&E to FAPRO 06/24/2009
    Consultant Contract Process Scope to DE 06/23/2008
    Consultant Contract Process NTP Issued 08/01/2008