| Project Description: |
ARLINGTON- BELMONT- CAMBRIDGE- RESURFACING & RELATED WORK ON ROUTE 2
The project will resurface Route 2 in Cambridge, Arlington and Belmont from milemarker 131.7 to 135.2, a distance of 3 miles. Some drainage improvements will be included.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Project Manager: | Albert Li![]() |
| Estimated Total Contract Cost: | $4,508,532.63 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 4 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
|
||