Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BARNSTABLE- BRIDGE PRESERVATION, B-01-019, ROUTE 6 OVER IYANQUGH ROAD (ROUTE 132)
The work to be done on this project involves minor rehabilitation to the bridge carrying Route 6 westbound and eastbound over Route 132, in the Town of Barnstable, Massachusetts. The work includes but is not limited to removing the bituminous wearing surface on the bridge deck and overlaying with an 1½" latex modified concrete; replacement of the expansion joints at the abutments; replacement of the joint over the pier with a link slab; adding thrie beam guardrail to the bridge parapet; cleaning (full removal) and painting of the entire existing structural steel as indicated in these contract documents; remove debris off the abutment bridge seats and coat the concrete surfaces, including abutment front face with an epoxy coating; repair concrete deteriorations at the abutments, wingwalls and piers.
Location:
  • Town of Barnstable
  • Resident Engineer: Malcolm Lavalley
    Construction Contract Value: $2,727,494.00
    Construction Bid Price: $2,144,777.77
    Initial Construction Estimate: $2,608,724.00
    District: District 5

    Contracts (2) Progress
    # 55039 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 66755 -- Construction Contract
    Bridge Rehabilitation (Including Painting) (B-01-019) - Route 6 over Iyannough Road (Route 132) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/18/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 02/03/2009
    Project Initiation Form PRC Submitted 09/28/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 08/21/2010
    Project Management
    100% Design 100% Package Received 07/30/2010
    100% Design 100% Package Comments to DE 02/23/2010
    75% Design 75% Package Received 09/08/2009
    75% Design 75% Package Comments to DE 11/24/2009
    Final Design PS&E Received 08/10/2010
    Final Design PS&E to FAPRO 08/17/2010