Project Description:
BEVERLY- SALEM- BRIDGE REPLACEMENT, B-11-005=S-01-013, KERNWOOD AVENUE OVER DANVERS RIVER AND B-11-001, BRIDGE STREET OVER BASS RIVER (HALL-WHITAKER DRAWBRIDGE)
A preliminary type study and a Value Engineering study shall help to determine whether this bridge should be replaced or rehabilitated. If replacement, then 3 options shall be explored: a fixed high span bridge; replacement of only the approach timber spans; and a complete bridge replacement with a movable span and fixed approach spans.
Location:
  • City of Beverly
  • City of Salem
  • Design Responsibility: Consultant
    Construction Begins: Autumn 2027
    Project Manager: Robert P Antico
    Estimated Total Contract Cost: $390,002,000.00
    Estimated Total Federal Participating Construction Cost: $406,252,100.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (2) Progress
    # 77879 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BEVERLY
    SALEM
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $71,044,214.40
    State Cost: $17,761,053.60
    Total Cost: $88,805,268.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Received 03/08/2012
    Project Initiation Form PIF Entered 03/08/2012
    Project Initiation Form PRC Submitted 03/08/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Management