Project Description: |
BEVERLY- SALEM- BRIDGE REPLACEMENT, B-11-005=S-01-013, KERNWOOD AVENUE OVER DANVERS RIVER AND B-11-001, BRIDGE STREET OVER BASS RIVER (HALL-WHITAKER DRAWBRIDGE)
|
Location: |
|
Design Responsibility: | Consultant |
Construction Begins: | Spring 2028 |
Project Manager: | Robert P Antico![]() |
Estimated Total Contract Cost: | $403,980,499.80 |
Estimated Total Federal Participating Construction Cost: | $422,696,924.20 |
Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
District: | District 4 |
Current Status: | 25% Package Received (as of 04/07/2025 ) |
|