Project Description:
BROOKFIELD- BRIDGE REPLACEMENT, B-26-002, SR 148 (FISKDALE ROAD) OVER THE QUABOAG RIVER
The existing two-span bridge is to be replaced with a single span superstructure of approximately 105 feet span. The superstructure system anticipated is either precast New England Boxed Tee or spread box beam stringers with an 8 inch HP 4000psi concrete deck and 3½ inch Hot Mix Asphalt wearing surface. The abutments are to be located behind the existing abutments, integral with the superstructure and supported on piles using the Bridge Manual details. The existing abutments shall be left in place to be part of the scour protection system and, if necessary, the construction dewatering system. They shall be cut down to facilitate inspection access to the new abutments and beam ends. The center pier shall be removed to either the mud line or the top of footing. This needs to be verified by the Geotechnical Report.
Location:
  • Town of Brookfield
  • Resident Engineer: David Windoloski
    Construction Contract Value: $4,052,917.00
    Construction Bid Price: $3,347,754.35
    Initial Construction Estimate: $3,699,050.05
    District: District 3

    Contracts (3) Progress
    # 59587 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 69759 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 79881 -- Construction Contract
    Bridge Replacement (B-26-002 ) (Precast Concrete) - Fiskdale Road (Route 148) over the Quabog River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/11/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 02/02/2009
    Project Initiation Form PRC Submitted 02/02/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/27/2009
    Project Status Advertised 09/21/2013
    Project Management
    25% Design 25% Package Received 12/05/2011
    25% Design 25% Package Comments to DE 10/01/2012
    25% Design Design Public Hearing 05/15/2012
    75% Design 75% Package Received 01/29/2013
    75% Design 75% Package Comments to DE 03/18/2013
    Final Design PS&E Received 06/24/2013
    Final Design PS&E to FAPRO 09/10/2013
    Consultant Contract Process Scope to DE 01/28/2010