DENNIS- BRIDGE REPLACEMENTS, D-07-001 & D-07-006, UPPER COUNTY ROAD & MAIN STREET (SR 28) OVER SWAN POND RIVER
The bridge carrying Upper County Road over the Swan Pond River is to be replaced with a three-span continuous superstructure. The existing abutments shall be removed and new abutments semi-integral with the superstructure and supported on steel H piles using the Bridge Manual details. Precast butted deck beams shall be used to minimize an increase in highway profile. The existing Main Street Bridge over Swan Pond River is to be replaced with a three-span continuous superstructure system. The curb-to-curb width of the bridge shall be 40 feet, with a 6 foot sidewalk on both sides. To minimize the depth of the superstructure, precast butted deck beams are to be used. During construction traffic will be shifted to a temporary bridge that will be built to the south of the existing bridge.
Location:
  • Town of Dennis
  • Resident Engineer: Malcolm Lavalley
    Construction Contract Value: $10,709,090.60
    Construction Bid Price: $8,953,139.50
    Initial Construction Estimate: $8,641,990.23
    District: District 5

    Contracts (6) Progress
    # 54830 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57466 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69764 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 73891 -- Construction Contract
    2 Bridge Replacements (Concrete) Br. No. D-07-001 Upper County Road and Br. No. D-07-006 Main Street (Route 28) Both over Swan Pond River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/16/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 02/03/2009
    Project Initiation Form PRC Submitted 02/03/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Status Advertised 06/09/2012
    Project Management
    25% Design 25% Package Received 03/29/2010
    25% Design 25% Package Received 03/25/2011
    25% Design 25% Package Comments to DE 08/06/2010
    25% Design Design Public Hearing 07/14/2011
    75% Design 75% Package Received 10/18/2011
    75% Design 75% Package Comments to DE 12/23/2011
    75% Design 75% Package Comments to DE 01/05/2012
    Final Design PS&E Received 03/05/2012
    Final Design PS&E to FAPRO 05/23/2012
    Consultant Contract Process NTP Issued 12/18/2009