Project Description:
DUXBURY- BRIDGE REPLACEMENT, D-14-010 (48H & 48J), ROUTE 3 (PILGRIM HIGHWAY) NB/SB OVER FRANKLIN STREET
The work for bridges, D-14-010 (48H & 48J), shall consist of removing the existing bridge superstructures, widening the existing abutments, and replacing with new superstructures complete with new decks and barriers. The new superstructures shall accommodate two lanes of traffic in their respective directions.
Location:
  • Town of Duxbury
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2023
    Project Manager: Theodore Boyle
    Estimated Total Contract Cost: $32,098,859.14
    Estimated Total Federal Participating Construction Cost: $33,412,500.75
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 03/25/2023 )

    Contracts (4) Progress
    # 58596 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 69755 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 69762 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77873 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 12/30/2010
    Project Initiation Form PRC Submitted 12/30/2010
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 03/25/2023
    Project Management
    25% Design 25% Package Received 02/07/2020
    25% Design 25% Package Comments to DE 05/12/2020
    25% Design 25% Package Received - Resub 1 02/22/2022
    25% Design Design Public Hearing 10/06/2022
    Final Design PS&E Received 10/04/2022
    Final Design PS&E to FAPRO 03/13/2023
    Consultant Contract Process Scope to DE 09/12/2011
    Consultant Contract Process NTP Issued 11/29/2011
    Consultant Contract Process Workhours Approved 10/26/2011