Project Description:
FITCHBURG- SUPERSTRUCTURE REPLACEMENT, F-04-011, CIRCLE STREET OVER NORTH NASHUA RIVER
The purpose of this project for the Circle Street Bridge over the Nashua River is to replace the deck, clean, prime, and paint all steel members, repair deteriorated steel members, and repair major concrete cracks and spalls on the substructure.
Location:
  • City of Fitchburg
  • Construction Begins: Autumn 2022
    Resident Engineer: Steven Miller
    Construction Bid Price: $2,369,000.00
    District: District 3

    Contracts (2) Progress
    # 120136 -- Construction Contract
    Bridge Superstructure Replacement Br. No. F-04-011 (Steel) Circle Street over North Nashua River Completed
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/28/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 09/30/2009
    Project Initiation Form PRC Submitted 09/30/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 09/03/2022
    Project Management
    100% Design 100% Package Received 04/11/2022
    100% Design 100% Package Comments to DE 05/13/2022
    25% Design 25% Package Received 02/06/2020
    25% Design 25% Package Received 07/09/2021
    25% Design 25% Package Comments to DE 05/07/2020
    25% Design 25% Package Received - Resub 1 01/22/2021
    25% Design Design Public Hearing 10/21/2021
    75% Design 75% Package Received 01/20/2022
    75% Design 75% Package Comments to DE 02/21/2022
    Final Design PS&E Received 05/31/2022
    Final Design PS&E Received - Resub 1 07/22/2022