Project Description:
GREAT BARRINGTON- BRIDGE REPLACEMENT, G-11-005, SR 183 (PARK STREET) OVER HOUSATONIC RIVER
The work for the Park Street bridge over the Housatonic River shall consist of removing the existing bridge superstructure and replacing with a new superstructure complete with new bridge railing, sidewalks, deck, and adjacent box beams. This project will require Multi-Phase Construction unless the city agrees to close the bridge and detour traffic.
Location:
  • Town of Great Barrington
  • Construction Begins: Summer 2016
    Resident Engineer: Richard Miskinis Jr
    Construction Bid Price: $3,227,304.75
    District: District 1

    Contracts (3) Progress
    # 77853 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 94156 -- Construction Contract
    Bridge Superstructure Replacement Br. No. G-11-005 (NEBT Beams) Route 183 (Park Street) over the Housatonic River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/22/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 02/12/2010
    Project Initiation Form PRC Submitted 02/12/2010
    Project Review Committee PRC Approved 01/02/2013
    Project Review Committee Letter 04/02/2010
    Project Status Advertised 05/07/2016
    Project Management
    100% Design 100% Package Received 06/24/2015
    25% Design 25% Package Received 10/16/2014
    25% Design 25% Package Comments to DE 11/25/2014
    25% Design 25% Package Comments to DE 03/26/2015
    25% Design 25% Package Comments to DE 06/03/2015
    25% Design Design Public Hearing 03/10/2015
    75% Design 75% Package Received 04/24/2015
    Final Design PS&E Received 12/21/2015
    Final Design PS&E to FAPRO 12/22/2015
    Final Design PS&E to FAPRO 04/28/2016