Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MARION- WAREHAM- BRIDGE REPLACEMENT, M-05-001=W-06-013 & W-06-016, MARION ROAD/WAREHAM ROAD (ROUTE 6) OVER WEWEANTIC RIVER
This project will consist of Structure Replacement for the bridge that is carrying US 6, Wareham Street, over the Weweantic River between the towns of Marion and Wareham. The existing structure was built in 1929 and then widened in 1957. The structure is structurally deficient, functionally obsolete, and critical. During the two stages of construction, one travel lane in each direction shall be maintained. If possible, one sidewalk shall also be maintained. The design consultant is responsible for preparation of the Project Traffic Management Plans (TMP) and if required, Work Safety Zone Protection Plans.
Location:
  • Town of Marion
  • Town of Wareham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2024
    Project Manager: Bryan J Cordeiro
    Estimated Total Contract Cost: $47,544,916.28
    Estimated Total Federal Participating Construction Cost: $49,958,261.15
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 25% Package Received (as of 01/05/2022 )

    Contracts (2) Progress
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77879 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MARION
    WAREHAM
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $32,775,512.00
    State Cost: $8,193,878.00
    Total Cost: $40,969,390.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 02/10/2009
    Project Initiation Form PRC Submitted 02/10/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Management
    25% Design 25% Package Received 01/05/2022