Project Description:
NATICK- BRIDGE REPLACEMENT, N-03-020, ROUTE 27 (NORTH MAIN STREET) OVER ROUTE 9 (WORCESTER STREET) AND INTERCHANGE IMPROVEMENTS
The project involves modifying the existing three quadrant cloverleaf interchange to provide a partial cloverleaf ramping system with auxiliary lanes on Route 9. The project includes replacing the substandard bridge, approach work, and drainage improvements.
Location:
  • Town of Natick
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2024
    Project Manager: Mustafa A Sadeq
    Estimated Total Contract Cost: $78,847,579.20
    Estimated Total Federal Participating Construction Cost: $85,752,072.55
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: 25% Package Received - Resub 2 (as of 09/25/2023 )

    Contracts (5) Progress
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64303 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NATICK
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Coronavirus Response and Relief Supplemental Appropriations Act
    Federal Cost: $46,901,244.00
    State Cost: $0.00
    Total Cost: $46,901,244.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 12/02/2010
    Project Initiation Form PRC Submitted 03/07/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Management
    25% Design 25% Package Received 05/13/2011
    25% Design 25% Package Received 01/12/2015
    25% Design 25% Package Received 02/12/2020
    25% Design 25% Package Comments to DE 06/10/2015
    25% Design 25% Package Received - Resub 1 05/16/2022
    25% Design 25% Package Received - Resub 2 09/25/2023
    25% Design Design Public Hearing 06/08/2017
    25% Design Design Public Hearing 06/15/2023