NEW MARLBOROUGH- SUPERSTRUCTURE REPLACEMENT, N-08-022, HADSELL STREET OVER UMPACHENE RIVER
The existing structure was constructed in 1938. The superstructure is composed of single span stringers with a reinforced concrete deck and bituminous concrete wearing surface. The overall bridge length is 45.9 feet, the curb to curb roadway width is 20.0 feet, and the out-to-out width of deck is 23.9 feet. There are no sidewalks. The substructure consists of two concrete gravity abutments and four concrete wingwalls on spread footings. The bridge was built with a 15 degree skew. The new superstructure structure shall be designed using the AASHTO LRFD Bridge Design Specifications and the Departments Bridge Manual with 2008 LRFD Bridge Design Guidelines. The bridge is to be replaced with a single span superstructure on the existing abutments. The superstructure system anticipated is the precast pre-stressed NEXT beams with an 8 inch HP 4,000 psi concrete deck and 3 1/2 inch HMA wearing surface. The existing abutment seats are to be removed and re-cast to accommodate the new superstructure using Bridge Manual details.
Location:
  • Town of New Marlborough
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Thomas Viscuso
    Construction Bid Price: $861,045.00
    District: District 1

    Contracts (5) Progress
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 58994 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 64319 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 97587 -- Construction Contract
    Bridge Superstructure Replacement Br. No. N-08-022 (Pre-Stressed Concrete) Hadsell Street over the Umpachene River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/10/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 05/30/2013
    Project Initiation Form PIF Entered 05/30/2013
    Project Initiation Form PRC Submitted 05/30/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 08/27/2016
    Project Management
    100% Design 100% Package Received 07/29/2016
    25% Design 25% Package Received 12/23/2015
    25% Design 25% Package Comments to DE 01/14/2016
    25% Design Design Public Hearing 04/06/2016
    75% Design 75% Package Received 06/02/2016
    Final Design PS&E Received 07/29/2016
    Final Design PS&E to Peer Reviewer 09/26/2016
    Final Design Peer Review Comments to DE 09/29/2016
    Final Design PS&E to FAPRO 08/22/2016
    Consultant Contract Process Scope to DE 10/04/2013
    Consultant Contract Process NTP Issued 04/03/2014
    Consultant Contract Process Workhours Approved 03/13/2014