Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
OXFORD- BRIDGE REPLACEMENT, O-06-030, (ST 56) LEICESTER ROAD OVER THE FRENCH RIVER
Location:
  • Town of Oxford
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: Herrio Lamothe
    Estimated Total Contract Cost: $3,448,962.64
    Estimated Total Federal Participating Construction Cost: $3,766,442.10
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: Design Public Hearing (as of 08/07/2024 )

    Contracts (1) Progress
    # 115753 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: OXFORD
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $4,067,757, Design Status = 25%, YOE = 8%
  • Category FA - Next Generation Bridge GANs
    Federal Cost: $3,254,205.60
    State Cost: $813,551.40
    Total Cost: $4,067,757.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 12/23/2014
    Project Initiation Form PRC Submitted 04/14/2021
    Project Review Committee PRC Approved 04/14/2021
    Project Management
    25% Design 25% Package Received 10/27/2023
    25% Design 25% Package Comments to DE 02/01/2024
    25% Design Design Public Hearing 08/07/2024
    Consultant Contract Process NTP Issued 06/06/2022