RAYNHAM- BRIDGE REPLACEMENT, R-02-013 (3PA), US 44 (CAPE HIGHWAY) OVER SR 24
The bridge is to be replaced with a 2-span continuous superstructure of approximately 103 feet (west span) and 121 feet (east span). The anticipated superstructure system is steel plate girders. Accelarated construction techniques such as roll-in / roll-out will be used to slide the new superstructure in place.
Location:
  • Town of Raynham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2017/2018
    Project Manager: Valerie E Kilduff
    Estimated Total Contract Cost: $23,515,040.26
    Estimated Total Federal Participating Construction Cost: $26,219,351.40
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 09/02/2017 )

    Contracts (2) Progress
    # 57464 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 77879 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 02/10/2009
    Project Initiation Form PRC Submitted 02/10/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Status Advertised 09/02/2017
    Project Management
    25% Design 25% Package Received 10/23/2015
    25% Design 25% Package Comments to DE 01/04/2016
    25% Design 25% Package Comments to DE 03/24/2016
    25% Design 25% Package Received - Resub 1 10/17/2017
    25% Design Design Public Hearing 01/12/2017
    Final Design PS&E to FAPRO 08/17/2017
    Consultant Contract Process NTP Issued 12/15/2010
    Consultant Contract Process Workhours Approved 12/10/2010