| Project Description: |
RAYNHAM- BRIDGE REPLACEMENT, R-02-013 (3PA), US 44 (CAPE HIGHWAY) OVER SR 24
The bridge is to be replaced with a 2-span continuous superstructure of approximately 103 feet (west span) and 121 feet (east span). The anticipated superstructure system is steel plate girders. Accelarated construction techniques such as roll-in / roll-out will be used to slide the new superstructure in place.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Valerie E Kilduff![]() |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 5 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||