SOUTHBOROUGH- BRIDGE PRESERVATON, S-20-018, I-495 (NB/SB) OVER HULTMAN AQUEDUCT & RAILROAD
The work for the bridge number S-20-018 shall consist of cleaning (full removal) and painting the structural steel and performing structural steel repairs to deteriorated superstructure members.
Location:
  • Town of Southborough
  • Resident Engineer: George Kamais
    Construction Contract Value: $4,734,902.94
    Construction Bid Price: $3,364,740.00
    Initial Construction Estimate: $4,065,200.00
    District: District 3

    Contracts (2) Progress
    # 64303 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 65714 -- Construction Contract
    Bridge Reconstruction (Including Painting) (S-20-018) (Steel) – Interstate 495 (NB & SB) over the Hultman Aqueduct and the CSX Railroad. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/29/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 10/30/2009
    Project Initiation Form PRC Submitted 11/16/2009
    Project Review Committee PRC Approved 12/02/2009
    Project Review Committee Letter 02/09/2010
    Project Status Advertised 06/26/2010
    Project Management
    100% Design 100% Package Received 05/27/2010
    Final Design PS&E Received 06/10/2010
    Final Design PS&E to FAPRO 06/23/2010